Delivered April 8th, 2003

Yahoo!

April 9, 2003 - Finishing Kit has arrived.  Starting inventory.

May 28, 2003 - First contemplation of Canopy.  Finished up wing nutplates.

May 29, 2003 - Installed Roll Bar.  What a pain....

June 4, 2003 - Roll bar brace drilled and bolted.  Started on canopy rollers.

June 5, 2003 - Assembled top canopy slide, set canopy on fuselage.

June 7, 2003 - Finished canopy frame bending and made first cut on canopy.

June 12, 2003 - Cut canopy to fit frame and drilled top of canopy to frame.

June 13, 2003 - Worked on canopy top strip and made another cut on front.

June 14, 2003 - Broke canopy frame, started on gascolator bracket.

June 15, 2003 - Mounted gascolator, transducer bracket, drilled firewall holes.

June 16, 2003 - Motor mount, had canopy frame welded and installing canopy.

June 17, 2003 - Worked on front windscreen (Windshield) all day.

June 18, 2003 - Finished front windscreen drilling, started on canopy latch.

June 24, 2003 - Finished canopy latch and drilled canopy rails and top slide.

July 1, 2003 - Canopy frame rear blocks. 

July 5, 2003 - Canopy side skirts, skirt braces, and inside skirts.

July 6, 2003 - Working on C-666 canopy aft skirts.

July 14, 2003 - Engine Control Brackets and Working on 'new' C-666 aft canopy skirts.

July 16, 2003 - Painted, etched, Alodined, and riveting canopy skirts to canopy frame. 

July 17, 2003 - Finished riveting canopy.... yep, 99% finished with the canopy, yahoo!

July 23, 2003 - Working on landing gear, Cleveland brakes and wheels.

July 24, 2003 - EAA inspection, nose wheel & tire, mounted nose gear.

September 21, 2003 - Working on panel vent tubing, glued vent to fuselage... hope it holds.

September 22, 2003 - Re-glued vent to fuselage, cut silicon from vent eyeball, oil press spacer.

October 9, 2003 - Finished Firewall Insulation and started working on routing control cables.

October 15, 2003 - Working on upper cowl. 

October 16, 2003 - Cut upper cowl to fuselage and started fitting lower cowl.

October 21, 2003 - Working on lower cowl.  Lots of work here.

October 23, 2003 - Cut bottom edge of lower cowl and re-drilled top cowl to fit better.

October 26, 2003 - Cut, sanded lower cowl to fit the top.  Installed lower hinge on firewall.

November 4, 2003 - Drilled top hinges to cowl, removed and working on side of fuselage. 

November 6, 2003 - Worked on the inside of fuselage, checked radio, installed cabin heat cable.

November 13, 2003 - Throttle cable, right brake line, worked on top fuselage skin (7106)

November 19, 2003 - Riveting 7106 top forward skin work, and left side skin along canopy rail.

November 20, 2003 - Finished right side of 7106 forward skin.  Working on left side. 

November 21, 2003 - Finished up left side of 7106 forward skin. 

November 22, 2003 - Working on Cowls, drilled tops, bottoms, and sides. 

November 23, 2003 - Started riveting hinges on top and bottom cowls. 

December 2, 2003 - Started working on the engine baffle kit.  Lots of work here...

December 3, 2003 - More work on the engine baffles.

December 6, 2003 - Yup, more engine baffle work. 

December 7, 2003 - Ohhh!  More baffle work.  Left floor almost done.

December 8, 2003 - Trimming top edges of baffles to mate with top cowl.

December 16, 2003 - Working on Oil Cooler flanges, and on the baffle seals.

December 20, 2003 - Finished engine baffle seals, installed oil cooler.

December 27, 2003 - Fiberglass some of  upper cowl, finished right brake, filled with brake fluid.

December 30, 2003 - Painted glareshield, set windscreen and canopy in place. 

December 31, 2003 - Working on windshield (windscreen) and canopy mating.  Lots of work here.

January 1, 2004 - Happy New Year!  First coat of fiberglass on windshield, and work on oil door.

January 6, 2004 - More resin work on the windshield and canopy area.

January 8, 2004 - Sanded windshield / canopy area and applied another coat of resin. 

January 12, 2004 - More work on the windshield, finished magneto and sparkplug wiring.

January 17, 2004 - Engine priming installed, working on windshield and battery brackets.

January 18, 2004 - Working on lower cowl rear bracket.  Tricky item...

January 19, 2004 - Battery mount done, 90% finished with exhaust mounts.

February 21, 2004 - Buttoned up the rear of the fuselage, seat belt cables, and painted windscreen.

February 22, 2004 - Put pilot seat in place to see what it looks like.   Real nice!

February 23, 2004 - Moving co-pilot headphone jacks, and mounting eye-ball vents in panel.

March 2, 2004 - Vertical Stab tip, SuperFil trial, and turned engine over for 20 psig oil pressure.

March 14, 2004 - Finished lower rudder tip, and started on the spinner assembly.

March 20, 2004 - More canopy fiberglass work and working on Propeller Nose Cone. 

March 23, 2004 - Finished nose cone, working on canopy finish, upper cowl finish, and started in on the intake. 

March 24, 2004 - Working on upper cowl finish work, sanded on canopy filler, and more work on the intake. 

March 28, 2004 - Finishing up filter box and lower cowl inlet scoop.  Lots of work here.

March 31, 2004 - Done with filter box. Made top cowl clip holder. Installed Navaid Servo.  Working on left wingtip

April 2, 2004 - Finishing up Wingtips and started working on the right Landing and Strobe/Navigation lights.

April 5, 2004 - Took a break from the Wingtips and put primer on the upper cowl, windshield border, nose cone, and canopy.

April 20, 2004 - Labeled dash, put on 'N' number, placards on dash, getting ready to move fuselage to airport.

June 12, 2004 - Working on Wheel Pants and Leg Fairings.  Lori started on the interior work. 

June 13, 2004 - Gained 28MPH with Wheel Pants and Leg Fairing.  (90% completed)