October 18, 2002 - The Fuselage Package arrives.

October 22, 2002 - Inventory of the Fuselage.

October 23, 2002 - Drilled Firewall bulkhead and most parts.

October 24, 2002 - Firewall Parts Primed and Clecoed.

October 25, 2002 - Finished Riveting the Firewall, looking at Bulkheads.

October 27, 2002 - Created Bulkhead parts, lots of aluminum shavings.

November 7, 2002 - Fished F-705 Bulkhead and straightening fuselage ribs.

November 11, 2002 - Finished Fuselage bulkheads.  Looking at longeron's.

November 18, 2002 - Bent Longeron's and assembled part of fuselage.

November 19, 2002 - Drilled J-Stiffeners and clecoed the aft fuselage.

November 23, 2002 - Started riveting aft fuselage.  Mom/Dad and rivet.

November 24, 2002 - Riveted aft tail cone.  Lori helps with the rivet gun.

November 29, 2002 - Finished up the aft fuselage today... Cool!

November 30, 2002 - Working on Center Fuselage today.

December 2, 2002 - Dimpled the Center Fuselage. More dimpling to do.

December 3, 2002 - Worked on Center Fuselage rib rivets. 

December 5, 2002 - Rivet center bottom skin, ready with longeron's.

December 6, 2002 - Attached center fuselage and installed side panels.

December 9, 2002 - Bending Conical bends and drilled longeron's to sides.

December 10, 2002 - Mounted firewall and bottom skin; drilled everything.

December 17, 2002 - More forward firewall constr. - start brake pedals.

December 21, 2002 - Brake and rudder pedals and floor stiffeners.

December 22, 2002 - Disassembled front end and started deburring parts.

December 27, 2002 - Debur and dimpled side skins, removed center fuse.

December 28, 2002 - Cut out landing holes, dimpled longeron's, and more.
December 29, 2002 - Putting the fuselage's back together. Lots of parts.

December 30, 2002 - Riveting skins on fuselage, about 1/2 done on skins.

December 31, 2002 - About 90% done with skins and bottom riveting.

January 1, 2003 - Finished skins and rolled the 'Canoe' over.  Cool!

January 2, 2003 - F-757, F-695, F-728A (Gussets and Angle pieces)

January 3, 2003 - Fashioned bellcrank part, just messed around today.

January 8, 2003 - Forward gussets, side rails, and canopy deck.

January 9, 2003 - Right canopy deck, drilled top skins, using Smart Tool!

January 10, 2003 - Riveted rear deck.... clean up shop some.

January 13, 2003 - Left step, gussets... flying day.

January 14, 2003 - Right step, baggage floors, started on rear panel.

January 16, 2003 - Finished baggage compartment.

January 18, 2003 - Finished tunnel cover, working on seats.

January 19, 2003 - More work on the seats.  Tedious job here....

January 27, 2003 - Finished seats, working on covers and flap actuator.

January 28, 2003 - Finished flap actuator and covers. 

January 29, 2003 - Installed landing gear mounts.

January 30, 2003 - Ordered gauges and started on HS Mounting.

January 31, 2003 - Mounted HS Stabilizer.

February 2, 2003 - Finished Elevator Control rod.

February 4, 2003 - Working on mounting Vertical Stabilizer to Fuselage.

February 5, 2003 - Finished up on Vert. Stab. and start on forward fuselage.

February 6, 2003 - More work on forward fuselage and air vents.

February 10, 2003 - Dimpled remaining skins, received instruments in mail.

February 14, 2003 - Working on elevator and stick controls.

February 16, 2003 - Built mount for Whelen strobe power supply.

February 22, 2003 - Painted 90% of the interior.

February 24, 2003 - Completed static tube installation.

February 25, 2003 - Installed map box ... 6 hours!

February 27, 2003 - EAA inspection, working on electrical.

March 5, 2003 - FWF delivery, install ELT, brake reservoir, Wally's RV8.

March 6, 2003 - Worked on some wiring, son helped out a little.

March 13, 2003 - Built Vertical Stabilizer again, put in new rudder stops.

March 15, 2003 - Working on battery box, engine parts came in.

March 22, 2003 - Rudder wiring, battery box finished, some strobe wiring.

March 23, 2003 - Cleaned garage, moved ELT mount, staring at Inst. panel.

March 24, 2003 - Relays on battery box, start attaching rudder cable.

March 25, 2003 - Rudder cable straps, fuel valve, elevator trim mount.

April 22, 2003 - Installed fuel tank brackets and cabin fuel vent lines.

May 20, 2003 - Fuselage fuel line to and from valve, right brake line.

May 21, 2003 - Left brake line, flexible brake hoses, and elevator trim cable.

June 2, 2003 - Working on fuselage top aft skins... rivet them in place.

June 4, 2003 - F-6111 braces and finished riveting Fuselage aft top skins.