Hangar Work

Airplane Home Page

Moved Fuselage to Hangar on 4/21/04

Yahoo!

April 21, 2004 - Moved Fuselage to Hangar

April 28, 2004 - Finished Wingtips and Moved Wings to Hangar. 

April 29, 2004 - Attached wings ... 8 hours worth. 

May 8, 2004 - Attached and set ailerons, flaps, compression, checked for usable fuel and quantity on gages, etc.

May 9, 2004 - First Engine Run.

May 15, 2004 - Weight and Balance done, Taxi tests done, stripping for EAA and DAR inspections.