Moved Fuselage to Hangar on 4/21/04
Yahoo!
April 21, 2004 - Moved Fuselage to Hangar
April 28, 2004 - Finished Wingtips and Moved Wings to Hangar.
April 29, 2004 - Attached wings ... 8 hours worth.
May 8, 2004 - Attached and set ailerons, flaps, compression, checked for usable fuel and quantity on gages, etc.
May 9, 2004 - First Engine Run.
May 15, 2004 - Weight and Balance done, Taxi tests done, stripping for EAA and DAR inspections.