Quick Built wings are here (April 8, 2003).... Yahoo!
April 9, 2003 - Wings have arrived, starting the inventory process.
April 11, 2003 - Built a Wing Sling to move the wings around with.
April 12, 2003 - Sort through lots of paperwork, installed left bellcrank.
April 13, 2003 - Snowed, aileron tubes.... not much today. Cold!
April 18, 2003 - Received landing lights and tie-down eyelets.
April 20, 2003 - Flap fairings, aileron gap fairings, aileron control tubes.
April 21, 2003 - Pushrod bell cranks, constructed aileron brackets.
April 23, 2003 - Installed Wing conduits, working on lower wing skin.
April 24, 2003 - Drilled, deburred, dimpled, installing lower wing skin.
April 29, 2003 - Finished left, working on right lower wing skin.
May 1, 2003 - Finished closing wings, mounted ailerons and flaps.
May 5, 2003 - Mounting Wings (Day One)
May 6, 2003 - Set wing incidences and drilled aft brackets.
May 8, 2003 - Drilled tank bracket nutplates, re-mounted ailerons.
May 9, 2003 - Aileron spacers and working on Flap settings.
May 11, 2003 - Moms Day- Worked mostly on Aileron travel settings.
May 16, 2003 - Wing root fairings, tank vents lines, removed wings.